Building a $2BN Skyscraper From Home | Summary and Q&A
![YouTube video player](https://i.ytimg.com/vi/4lnncgMCLKA/hqdefault.jpg)
TL;DR
Sydney's tallest building, Crown Sydney, overcame challenges caused by the pandemic with the help of digital collaboration tools.
Key Insights
- π§ Crown Sydney is a remarkable mega project, standing as the tallest building in Sydney, with a unique curved design inspired by nature.
- ποΈ The construction of the tower's basement using a top-down approach reduced the overall build time significantly.
- π½οΈ The project faced unexpected challenges due to the COVID-19 pandemic, but digital collaboration tools like Bluebeam Review enabled remote work and kept the project on schedule.
- π The use of digital tools in construction, such as Bluebeam Review, is becoming increasingly common, enabling paperless projects and facilitating communication and collaboration.
Transcript
rising 275 meters above the famous harbour crown sydney is about to become the city's tallest building with a striking form and cutting edge engineering the 2.2 billion australian dollar skyscraper quickly emerged as one of the country's most impressive mega projects but as the tower topped out and neared completion the coronavirus pandemic hit the... Read More
Questions & Answers
Q: What are the key features of Crown Sydney?
Crown Sydney is a 71-storey structure that includes a six-star hotel, VIP casino, and high-end apartments. It also has two rooftop infinity pools and ground-level podium with shops and cafes.
Q: How did engineers achieve the tower's unique curved form?
Engineers used a combination of a concrete core and a steel and concrete superstructure. Raking columns supported the tower's 60-degree twist, and a 200-ton tuned mass damper ensured stability against lateral forces.
Q: How did the project team tackle the challenge of building the basement?
They adopted a top-down approach, simultaneously building the tower above ground while steadily excavating the basement below. This approach reduced the overall build time by over 12 months.
Q: How did the project team manage to complete the complex fit-out remotely during the pandemic?
The team had previously invested in digital collaboration tools like Bluebeam Review. This allowed them to communicate in real time, mark up documents, and track issues and comments, ensuring the project stayed on track.
Summary & Key Takeaways
-
Crown Sydney, a $2.2 billion skyscraper, rises above Sydney's regenerated Barangaroo district, offering stunning views of the city.
-
The tower's unique curved form, inspired by nature, required innovative engineering solutions, including a concrete core and a steel and concrete superstructure.
-
Despite the challenges posed by the pandemic, the project team successfully completed the tower's complex fit-out remotely using digital collaboration tools like Bluebeam Review.
Share This Summary π
Explore More Summaries from The B1M π
![The Secret Security of America's London Embassy thumbnail](https://i.ytimg.com/vi/2G-HdtbO4CI/hqdefault.jpg)
![Building Chinaβs $12BN Mega Airport thumbnail](https://i.ytimg.com/vi/-aWJ5p3X-Yo/hqdefault.jpg)
![Delivering New Karolinska Solna Hospital with BIM | The B1M thumbnail](https://i.ytimg.com/vi/1prdJd7-zww/hqdefault.jpg)
![Top 5 Stadium Builds by 2020 thumbnail](https://i.ytimg.com/vi/2D1udIMtVok/hqdefault.jpg)
![Is America Finally On Track With High-Speed Rail? thumbnail](https://i.ytimg.com/vi/-6W3Kv6mMzc/hqdefault.jpg)
![Bringing Star Wars Galaxy's Edge to Life thumbnail](https://i.ytimg.com/vi/19vjWwvgS2g/hqdefault.jpg)